Timeline and Gantt chart share a similar view of the tasks list and the calendar, however they are different in some points

  • Task hierarchy in Timeline is Hierarchy: In the Timeline, the task hierarchy follows the Issue hierarchy in Jira (Initiatives → Epic → Issue → Sub-task) while . In contrast, the Gantt chart maintains uses a custom hierarchy based on the Work Breakdown Structure (WBS) numbernumbering.

  • Advanced Features in Gantt Chart: The Gantt chart provides includes advanced Gantt features such as baseline tracking, critical path identification, inline task creation, drag&drop and the ability to update task hierarchy via drag and drop. Timeline doesn’t have those features.

...

  • These features are not available in the Timeline.

  • Usage Options: You have the flexibility to use either the Timeline or the Gantt chart, or both, depending on your needs. This can be configured in the Feature settings

...

The Complete Table Feature of Gantt and Timeline

Feature

Gantt

Timeline

Issue Table Detail

(tick)

(tick)

Dependency

(tick)

(tick)

Milestone

(tick)

(tick)

Progress

(tick)

(tick)

Quick Filter

(tick)

(tick)

View Setting

(tick)

(tick)

Hierarchy

Follows the Issue hierarchy in Jira (Initiatives → Epic → Issue → Sub-task)

Custom hierarchy based on the Work Breakdown Structure (WBS

Dependency

(tick)

(error)

Baseline

(tick)

(error)

Critical Path

(tick)

(error)