Please keep in mind that when mapping date fields to Jira fields the app follows Jira’s spec and some advanced feature such as scheduling task multiple times or planning 1 task for many users are not supported.
You can configure this from Project Board
...
Settings or from App
...
Settings.
From
...
TeamBoard within the project, click the
...
settings cog on the right to
...
go to Board Settings →
...
Field Settings.
Turn on the option
...
'Map dates with Jira fields
...
' and select the Jira fields you want to map to the Start date and End date.
...
Depending on your project's Screen Scheme, the issue types in the project may not have the fields you
...
've selected. This list displays the current statuses.
...
Issue types that don't have the
...
required fields won't function properly, so you should add
...
these fields to the Screen of those issue types
...
Click Save to save the settings, after saving you can migrate the existing start dates and end dates exists in App’s data to Jira fields ( this is one a way migration from App to Jira )
After configuring correctly, issues in the project will use Jira fields when planning with ProScheduler
In App Settings
You can also configure the fields mapping for each project from App Settings
From Jira go to Apps → TeamBoard ProScheduler → Settings → Fields Settings
Select the project you want to configure in the dropdown list, then the same configuration with project board settings appears and you can map the fields
...