...
Info |
---|
Please note that when mapping date fields to Jira date fields is enabled, the app follows Jira’s specs, and some advanced features such as scheduling tasks multiple times or planning one task for many users adheres to Jira's specifications. As a result, advanced features like scheduling a task multiple times for different users or planning recurring tasks are not supported. |
From Jira go to Apps → TeamBoard TimePlanner → Settings → Date Fields Mapping
Search the project name.
Select the project you want to configure in the dropdown list, and then Turn on .
Toggle ON the “Map dates with Jira fields” button
Select the Jira fields you want to map to the Start date and End date.
Tip |
---|
If your configuration matches with the project settings, you can map the fieldsyou have a valid configuration, the issue types should be marked with green check icons in both field columns. Next step: Click on the Save button → then click on Migrate to finish the mapping. |
...
Warning |
---|
Depending on your project's Screen Scheme, the selected fields may not be available for certain issue types. To ensure proper configuration, you need to add the fields to the Screen of those issue types that lack them. |
...