Task Progress

 

 

Manage task progress

  • Slide on the bar to edit the progress

  • or edit it in the Issues table

Board admin can configure the Progress field in Board settings

Progress Field Setting

This setting can be found in Board Settings → Gantt

In WBS Gantt chart, the user can maintain the progress of each task.

Progress field: The data source

  • Default: the value will be stored in the app

  • Jira field: map with Jira field

  • Auto: it is calculated from logged time and scheduled time

Ascendant Progress: How to calculate the progress of parent task

  • Based on descendants: calculated from the progress of the descendants

  • Actual value: the value of its Progress field value