The Timeline feature allows users to create a visual representation of the task schedule for a project. This feature helps project managers and team members to track project progress, identify potential roadblocks and dependencies, and adjust the project plan accordingly.

The timeline displays tasks with Issue hierarchy in Jira, start and end dates, duration, and other relevant information. It provides a clear overview of the project schedule, making it easier to understand and communicate project status to stakeholders.

Screenshot 2024-10-08 at 17.25.48.png

1. Timeline menu

Screenshot 2024-10-08 at 17.38.52.png
  • Refresh Screenshot 2024-10-08 at 17.43.41.pngUpdates the timeline with the latest data without needing a full page refresh.

  • Full-screen mode Screenshot 2024-10-08 at 17.41.23.png: Expands the Timeline view to fill the entire screen.

  • Board Settings Screenshot 2024-10-08 at 22.07.26.png: Access and adjust board settings and preferences.

  • Help Center Screenshot 2024-10-08 at 22.07.44.png: Opens helpful resources for assistance and support in ProScheduler

2. Timeline toolbar

Screenshot 2024-10-08 at 22.12.43.png
  1. Search and Filter Issue: Search for specific issues and apply filters to narrow down the view.

  2. Hierarchy: Toggle to show or hide the issue hierarchy within the timeline.

  3. Show Issues: Expand or Collapse issues on specific projects on the timeline

  4. Sort By: Sort issues based on selected criteria: Issue key, Summary, Start date, End date, Fix versions, and Status.

  5. Group By: Group issues by categories: Status, Assignee, Issue Type, Priority, Fix version, and Sprint.

  6. Quick Filter: Apply filters to view specific issues based on JQL settings.

  7. Save view Screenshot 2024-10-08 at 22.50.58.png : Save your customized views in the Timeline, enabling you to retain preferred layouts and settings for future use.

  8. Import button Screenshot 2024-10-08 at 22.30.24.png Import tasks from CSV feed into specific projects in Jira

Screenshot 2024-10-08 at 17.33.23.png
  1. Export button Screenshot 2024-10-08 at 22.30.29.png Export issues to an XLSX file, allowing users to download the timeline based on selected criteria.

Screenshot 2024-10-08 at 22.38.11.png
  1. View settings Screenshot 2024-10-08 at 22.30.35.png customize the display of the timeline.

Screenshot 2024-10-07 at 17.31.56.png

Here are descriptions of view settings:

Settings

Descriptions

  1. Show completed tickets

Displays tasks or tickets that have been marked as completed.

  1. Column divider

Adds a visual divider between different columns in the timeline.

  1. Highlight day off

Highlight days off (like weekends or holidays) as Gray color on the timeline

  1. Show issue key

Displays the unique identifier (issue key) for each task or ticket

  1. Show issue summary

Shows a brief summary of each task or issue directly in the timeline

  1. Show details tooltip

When hovering over a task, this option provides a tooltip that displays additional information about the task, such as status, assignee, or time remaining.

  1. Show Progress

Displays a visual representation of task progress, allowing users to track how far along each task is toward completion.

  1. Show duration

Shows the total duration of each task, providing a clear view of how long the task is scheduled to take on the timeline.

  1. Show issue overdue

Highlight overdue issues.

  1. Mark non-working days

Marks non-working days (such as weekends or holidays) on the timeline

  1. Hide weekend days

Exclude weekends from the timeline view

  1. Show project duration

Displays the overall duration of the project which displays the total duration of a project based on the earliest start and latest end dates