Global configuration for WBS Gantt feature, the board-level configuration can be found in Board settings

To access go to AppsTeamboard ProSchedulerSettingsGantt

Auto scheduling: when enabled the plan will be automatically re-calculated when changing children task or dependencies

Auto-scheduling doesn’t take effect on tasks that have multiple plans and assignee

Support adjusting the lag time in the Gantt chart

Support adjusting the lag time between tasks directly in the Gantt chart when auto-scheduling is ON.

When auto-scheduling is enabled, changes in lag time are automatically applied across linked tasks to maintain accurate schedules.

  • Click on a dependency link, and then add lag time to it

Support adjusting the lag time in the Gantt chart when auto-scheduling is ON..png

Troubleshooting Tips:

  • If changes aren't reflected, ensure that auto-scheduling is enabled.

  • Verify that the tasks are properly linked via dependencies.

  • Refresh the Gantt chart to apply any pending updates.