In addition to the timeline which reuse Jira Issue hierarchies, from the version 1.4.47 Cloud and 7.0.0 for Server/Data Center we support the WBS Gantt, it maintains a custom hierarchy and provides advanced Gantt feature such as Critical Path, Baseline, Milestone
Initiate WBS Gantt
By default the WBS Gantt is enabled by default, when it is accessed for the first time the current hierarchy in Timeline will be copied and assigned the Work-Breakdown-Structure (WBS) number accordingly. The changes afterward will be maintain in the WBS order and not synced with Jira Issue hierarchy TImeline. WBS Gantt can be disabled by Jira admin or the board admin.
WBS Gantt Menu
Menu
Search and Filter issue