Task Progress

In WBS Gantt chart, user can maintain the progress of each task.

Progress field: The data source

  • Default: the value will be stored in app

  • Jira field: map with Jira field

  • Auto: it is calculated from logged time and scheduled time

Ascendant Progress: How to calculate the progress of parent task

  • Based on descendants: calculated from progress of the descendants

  • Actual value: the value of its Progress field value

Color pattern: UI look&feel on the Gantt bar

Baseline

Baseline color patterns: configure the color of the baseline bar, default is gray