Manage progress

  • Slide on the bar to edit the progress

  • or edit it in the Issues table

Board admin can configure the Progress field in Board settings

Image AddedImage Added

Configuration options to customize WBS Gantt chart feature.

Gantt setings can be found in Board SettingsGantt

Image Modified

Task Progress

In WBS Gantt chart, user can maintain the progress of each task.

Progress field: The data source

  • Default: the value will be stored in app

  • Jira field: map with Jira field

  • Auto: it is calculated from logged time and scheduled time

Ascendant Progress: How to calculate the progress of parent task

  • Based on descendants: calculated from progress of the descendants

  • Actual value: the value of its Progress field value