Task Progress
Â
Â
Manage task progress
Slide on the bar to edit the progress
or edit it in the Issues table
Board admin can configure the Progress field in Board settings
Progress Field Setting
This setting can be found in Board Settings → Gantt
In WBS Gantt chart, the user can maintain the progress of each task.
Progress field: The data source
Default: the value will be stored in the app
Jira field: map with Jira field
Auto: it is calculated from logged time and scheduled time
Ascendant Progress: How to calculate the progress of parent task
Based on descendants: calculated from the progress of the descendants
Actual value: the value of its Progress field value